I had earlier blogged on the judgment of a Division bench
of the Delhi High Court in Dr.Alloys Wobben v.
Yogesh Mehra & Ors. delivered on January 20, 2012, in which the the DB had held that both
a counter-claim and a revocation petition could be explored simultaneously
against the same patent.
Litigation between the Parties
In a
related contractual dispute between the parties which appears to be the root of all contentions between the parties, the Bombay High Court
delivered its decision (available here) on October 5, 2012 in
Writ Petitions filed by Enercon India against orders passed by the District
Judge of Daman. According to the decision, both warring factions have been directed to resolve their disputes through arbitration provided for in the Intellectual Property License Agreement (IPLA) previously entered into between the parties.
The detailed facts leading to the writ petitions are as follows:
The detailed facts leading to the writ petitions are as follows:
1. Petitioners/Plaintiffs: Enercon India, Yogesh Mehra and Ajay Mehra (Mehra
brothers are directors of Enercon India)
2. Respondents/Defendants: Enercon GmBh (Dr.Alloys Wobben is its Director) and
Wobben Properties Gmbh
3. Shareholding Pattern in Enercon India (Joint
Venture Company): Enercon GmBh- 56%,
Mehra Brothers- 44%
4. Owner
of Patents on Windmill technology- Wobben Properties Gmbh, Licensor- Enercon
GmBh, Licensee- Enercon India
5. A
Technical Know-How Agreement was entered into in 1994 between Enercon GmBh and
Enercon India under which Enercon Gmbh agreed to transfer to Enercon
India the right and the technology to use the technical know-how for the
manufacture of E-26 Wind Turbine Generators
6. A
Supplementary Technical Know-How Agreement entered into
in 2000 amended the 1994 agreement and granted a licence to Enercon India to manufacture
the E-30 and E-40 Wind Turbine Generators.
7. The Agreement
expired in 2004, however Enercon GmBh continued to supply Wind Turbine
Generators and components to Enercon India.
8. In 2006,
parties entered into a comprehensive arrangement by
the name “Agreed Principles” which governed the use and supply of windmill
technology. Under the Agreed Principles, parties further entered into an Intellectual Property License Agreement ("IPLA")
on September 29, 2006, which was the subject matter of the dispute between the
parties in the Writ Petitions.
According to Enercon India:
A. “the Agreed Principles are the binding
principles agreed between the parties, and which records an agreement that all
definitive agreements between the parties that were to be prepared and finally
executed would be on the basis of the binding principles agreed therein. One of
the agreements contemplated by the said Agreed Principles was the IPLA”
B. “the IPLA signed in September 2006 was merely
a draft of the oral terms and not a concluded contract between the parties. It
was their case that the said document was an unincorporated and inchoate
document and was not a concluded contract”
C. This,
according to Enercon India, was supported by a communication received by it from
a representative of Enercon Gmbh dated October 4, 2006 in which it was conveyed
by the representative that she “would try
her best to prepare/adapt the agreements according to the Agreed Principles”.
D. On October
18, 2006, the same representative informed Enercon India that the IPLA signed
in September 2006 was the final document.
Subsequent to
this, parties exchanged notices arguing on whether or not the IPLA was final and
binding. Enercon GmBh stopped supplying generators and components to Enercon
India and litigation ensued, which is captured in brief below:
Litigation between the Parties
i. Enercon India
filed a suit before the Bombay HC seeking an interim relief to the effect that supply
of generators and components be resumed. Enercon GmBh did not comply with the
order, resulting in the filing of a contempt petition against it by Enercon India.
ii. In response, Enercon GmBh
moved the Company Law Board, Delhi for removal of Mehra brothers as directors of
Enercon India. The Mehra brothers in turn filed a company petition against Enercon
BmBh for oppression and mismanagement.
iii. Besides, Enercon
GmBh also secured an ex parte injunction
from the Hamburg District Court against Enercon India restraining the latter
from supplying generators under the trademarks of Enercon GmBh. The injunction was
subsequently set aside by the Hamburg Court on grounds of lack of evidence against
Enercon India.
Finally in March
2008, Enercon GmBh evinced interest in settling all outstanding disputes with
Enercon India, including the question of the IPLA, and invoked the arbitration
clause provided for in the IPLA. Enercon India responded stating that since the
IPLA was not a concluded contract, there was no valid arbitration agreement in
place. Also, according to Enercon India, by its litigious conduct Enercon GmBh had waived the arbitration
agreement.
Enercon GmBh then
filed for a declaratory judgment in a UK Court against Enercon India, inter alia seeking an
anti-suit injunction against Enercon India to restrain it from continuing with
the suit proceedings before the Bombay High Court.
On its part, Enercon India
filed a suit before Senior Division Judge, Daman seeking – “a declaration that the IPLA was not a
concluded contract and correspondingly that there was no Arbitration Agreement
between the parties; for a declaration that the initiation of proceedings
before the English Court by the Respondents was void and illegal; and for a
permanent injunction restraining the Respondents from continuing with the
proceedings before the English Court”.
The Senior Division Judge, Daman passed an ex parte order restraining Enercon GmBh
from proceeding with the suit before the UK Court. Subsequently, Enercon GmBh appeared before the Daman
Judge and moved an application under Section 45 of the Arbitration Act
contending that the suit must be referred to arbitration under the IPLA. The
Senior Division Judge dismissed Enercon GmBh’s application and confirmed the anti-suit
injunction.
Enercon GmBh
appealed to the District Judge, Daman who set aside the decision of the Senior
Division Judge on the grounds that since the Mehra Brothers had signed in the
IPLA in September 2006, it was a concluded contract, and hence the arbitration
clause was valid.
Against this
decision of the District Judge, Enercon India and Mehra brothers preferred writ petitions before the Bombay High Court.
Writ Petitions before the Bombay High Court
In the
Writ Petitions filed by Enercon India and the Mehra Brothers (Petitioners), the Bombay High Court concluded that the IPLA was a concluded
contract, and that the arbitration agreement too was valid, based on the
following reasons:
A. 19.The inquiry contemplated under Section 45
is therefore of a prima facie nature of the existence of an Arbitration
Agreement. If the Court comes to a prima facie conclusion that there is an
Arbitration Agreement and the same is legal and valid, the matter must be
referred to the Arbitral Tribunal for further consideration which can
thereafter conclusively decide either way. If the Court comes to the prima
facie conclusion that there is either no Arbitration Agreement or that the same
is not valid in law, the Court must then proceed to determine the same finally
and conclusively.
B. 22.... The aforesaid Judgments of the Apex
Court as well as the United States Supreme Court, make it clear that the
Arbitration Agreement would survive even in case of invalidity of the main
agreement or the underlying contract. It is only in cases where the underlying
contract is vitiated by fraud, coercion or misrepresentation that the same
would impact the Arbitration Agreement. 23 The principles of severability and
separability of the Arbitration Agreement is common both under the English
Arbitration Act, 1996 and the Indian Arbitration Act 1996...
C. 24....The Learned Senior Counsel for the
Petitioners laid much store on the correspondence post 29-9-2006 i.e. the date
when the IPLA was signed, to contend that the IPLA was not a concluded
contract. However, the correspondence prior thereto between the parties
indicates otherwise. If the said correspondence is seen, to which my attention
is drawn by the Learned Senior Counsel appearing for the Respondents, the same
discloses that it was on 27-6-2006 i.e. a good three months prior to its
execution,that the draft IPLA was sent to the Petitioners. The said IPLA had
already undergone changes on the basis of the suggestions of both the parties
and the final document was kept ready on 29-9-2006 as the Petitioner No.2 had
shown his inability to come to Aurich on 17-9-2006 when it was to be executed.
D. 24.... The most important
letter if it can be said so, is the letter dated 30-9-2006 which is addressed
by the Petitioner No.2 Yogesh Mehra in his own handwriting stating therein that
he has executed not one but more than one agreement on 29-9-2006. Pertinently
in paragraph 2 of the said letter, the Petitioner No.2 has in fact referred to
the patent of E-82 being the subject matter of the IPLA and not the Agreed Principles
E. 29. The defining aspect is the intention
of the parties to go for arbitration which intention is clearly manifest in the
IPLA.
F. 37 This Court has taken a prima facie view that there is in
existence an Arbitration Agreement and therefore the parties can be referred to
arbitration. In so far as instant Petition i.e. Writ Petition No.7636 of 2009
is concerned, the question is whether the Petitioners are entitled to an anti
suit injunction, and whether the English Courts have jurisdiction.
G. 38 The adjudication of the said aspect therefore
revolves around the interpretation of clause 18.3 of the IPLA. For the sake of
convenience, the said clause 18.3 is revisited herein under for the purposes of
the present Petition. "Clause 18.3---- All proceedings in such arbitration
shall be conducted in English. The venue of the arbitration proceedings shall
be London. The arbitrators may (but shall not be obliged to) award costs and
reasonable expenses (including reasonable fees of counsel) to the Party(ies)
that substantially prevail on merit. The provisions of the Indian Arbitration
and Conciliation Act, 1996 shall apply"
On the basis of this clause, the Bombay High
Court finally concluded as follows in Para 55:
55. On an interpretation of clause 18.3 of the IPLA this
Court has reached a conclusion that the curial law or Lex Arbitri would be the
Indian Arbitration Act. Though the Indian Arbitration Act would apply, however,
in view of the fact that the parties have chosen London as the venue for the
arbitration meetings, the English Courts would have concurrent jurisdiction and
therefore the jurisdiction of the English Courts can also be invoked by the
parties for taking such measures as are required in support of arbitration. The
judgment and order of the Lower Appellate Court on the aspect of anti suit
injunction is, therefore, sustained but on a different ground which is
mentioned in the body of this Judgment.
No comments:
Post a Comment